Controls are statements that determine how the network is operated over time. They specify the status or setting of selected links as a function of time, tank water levels, and pressures at select points within the network. There are two categories of controls that can be used:
•Simple Controls
•Rule-Based Controls
Simple controls change the status or setting of a link, based on:
•the water level in a tank,
•the pressure at a node,
•the time into the simulation,
•the time of day.
Rule-Based Controls allow link status and setting to be based on a combination of conditions that might exist in the network, after an initial hydraulic state of the system is computed.